Projects

Below are the list of ongoing and past projects of Rigde Maha Guru Reteat Center:



Project Name: Achievement of Slap Casting
Construction Cost: Nu. 86,400.00
Commencement Date: 22th August, 2016
Project Period: 2 days
Status: Completed
Detail: In spite of so many hindrances, the long awaited slab casting is now finally completed. The practitioners/members from Samdrup Jongkhar, Bangtar, Pemagatshel and other areas have tirelessly put in their efforts to achieve this success. In the first day there were 147 workers of which 40 helpers were our dedicated practitioners, Indian laborers and few other villagers who came to dedicate their kind service for the casting work. However, there were only 100 workers to work for the slab casting in the second day. People from Sarjung, Wangphu, Shemshem and tsholingkhar were also present there to turn the wheel of Dharma.
The slab casting was commenced from 22th August, 2016 to 23rd August, 2016. The labour cost incurred during the casting was Nu. 86,400/- (eighty six thousand four hundred only) inclusive of wages paid to the members, but our dedicated dharma friends have decided to reserve the remuneration for other future benefits of our own RMGC.
I on behalf of H.E. Chabje Rinpoche, the RMGC administration and members/practitioners all around the nation would like to extend our warm heartfelt gratitude towards all the people who were involved in the work of slab casting.
Nevertheless, the administration would like to thank our root guru for his continuous blessing and being an instrumental in achieving all the success so far. And also administration would like to thank our dedicated members/ practitioners for your unstinting support in conducting Selkha (conducting prayer to please dharma protectors) as per the instructions of H.E Chabje Rinpoche.

Project Name: Slab Casting Ready
Construction Cost: currently not known
Commencement Date: Not fixed
Project Period: 1 to 2 days
Status: On Halt
Detail: The slab casting is being delayed because of the heavy rainfall and road blocks at and around the site. Hopefully, immediately after the peaceful weather the slab casting will be commenced.

Project Name: Current developments
Construction Cost: The cost not known
Commencement Date: 02/02/2016
Project Period: 2 months
Status: Completed
Detail: The 16000 Ltr Water tank is completed and expected to solve water shortage in the future.
Currently a fully constructed Ngoezhi Tshamkang is housing a ngoezhi tshapa.



News & Events

  • Birth Anniversary of HE. Jigme Rig

    Aug 13, 2018 - Media (RMGC): Media (RMGC): Yesterday on 12/8/2018 RMGC Thimphu has organised program to mark the...

    more
  • Notification of election.

    Jul 31, 2018 - Election Notice. RMGC Administration notifies that, With effect from 1st Aug till Oct 2018, all mem...

    more